What are the two options available in the PartSourceType.TransitRule field for calculating lead time?

Study for the Kinaxis Certified Maestro Author Level 1 Test. Prepare with flashcards and multiple-choice questions, each question comes with hints and explanations. Get ready for success!

The correct choice provides two options for the PartSourceType.TransitRule field specifically concerning the calculation of lead time within supply chain processes. "Cumulative" refers to lead times that incorporate all factors or stages in a series of processes, thereby providing a comprehensive total lead time. This method aggregates individual lead times from each segment in the supply chain to ensure that the cumulative timing reflects the overall time required for the entire process.

"Inclusive," on the other hand, indicates that the lead time not only takes into account the time directly associated with a given process but also includes any additional time factors that may influence the lead time, such as delays or variations in production or shipping. This term emphasizes that when calculating lead times, all relevant periods or factors should be considered together.

Understanding these concepts is crucial for accurate lead time calculations, as they help in making informed decisions about inventory management and supply chain efficiency.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy